Project Record
First Electronics
CFS wall panels and a framed mezzanine for The First Electronics Corporation facility fit-out in Braintree, Massachusetts.
Project Overview
Project gallery
Field views from CFS wall and arch framing through mezzanine floor installation and the completed lobby.
Scope
CFS work completed for this project
-
01
Phase 1 wall package
Wall layout plan and individual FRAMECAD panel sheets for wall panels L1–L41, L124 and L125, framed with 6-inch and 3-5/8-inch studs, plus ceiling panel C1.
43 WALL PANELS 600S162-33 + 362S162-27 CEILING PANEL C1 -
02
Mezzanine walls and parapet
Mezzanine wall plan with panels M1–M21 and parapet panels M22–M24, including header-framed openings and east, north, south and west elevations.
21 WALL PANELS 3 PARAPET PANELS 4 ELEVATIONS -
03
Mezzanine floor framing
Floor plan with 24 CFS floor trusses (PC1 ×13, PC2 ×11) designed for a 100 psf top-chord live load and 40 psf dead load, plus joists and beams at edges, openings and supports.
24 FLOOR TRUSSES 100 PSF LIVE LOAD AISI S100-20 LRFD